§ 27.303 Upper 700 MHz commercial and public safety coordination zone.
(a) General. CMRS operators are required, prior to commencing
operations on fixed or base station transmitters on the 776-787 MHz
band that are located within 500 meters of existing or planned public
safety base station receivers, to submit a description of their
proposed facility to a Commission-approved public safety coordinator.
(i) The frequency or frequencies on which the facility will operate;
(ii) Antenna location and height;
(iii) Type of emission;
(iv) Effective radiated power;
(v) A description of the area served and the operator's name.
(2) It is the CMRS operator's responsibility to determine whether
referral is required for stations constructed in its area of license.
Public safety base stations are considered "planned" when public safety
operators have notified, or initiated coordination with, a
Commission-approved public safety coordinator.
(b) CMRS operators must wait at least 10 business days after submission
of the required description before commencing operations on the
referenced facility, or implementing modifications to an existing
facility.
(c) The potential for harmful interference between the CMRS and public
safety facilities will be evaluated by the public safety coordinator.
(1) With regard to existing public safety facilities, the coordinator's
determination to disapprove a proposed CMRS facility (or modification)
to be located within 500 meters of the public safety facilities will be
presumed correct, but the CMRS operator may seek Commission review of
such determinations. Pending Commission review, the CMRS operator will
not activate the facility or implement proposed modifications.
(2) With regard to proposed public safety facilities, the coordinator's
determination to disapprove a proposed CMRS facility (or modification)
to be located within 500 meters of the public safety facilities will be
presumed correct, but the CMRS operator may seek Commission review and,
pending completion of review, operate the facility during construction
of the public safety facilities. If coordination or Commission review
has not been completed when the public safety facilities are ready to
operate, the CMRS operator must cease operations pending completion of
coordination or Commission review. Such interim operation of the CMRS
facility within the coordination zone (or implementation of
modifications) will not be relied on by the Commission in its
subsequent review and determination of measures necessary to control
interference, including relocation or modification of the CMRS
facility.
(d) If, in the event of harmful interference between facilities located
within 500 meters proximity, the parties are unable, with the
involvement of the coordinator, to resolve the problem by mutually
satisfactory arrangements, the Commission may impose restrictions on
the operations of any of the parties involved.
[ 67 FR 49245 , July 30, 2002, as amended at 72 FR 48853 , Aug. 24, 2007;
79 FR 599 , Jan. 6, 2014]
return arrow Back to Top
CiteFind - See documents on FCC website that
cite this rule
Want to support this service?
Thanks!
Report errors in
this rule. Since these rules are converted to HTML by machine, it's possible errors have been made. Please
help us improve these rules by clicking the Report FCC Rule Errors link to report an error.