Goto Section: 101.1007 | 101.1011 | Table of Contents

FCC 101.1009
Revised as of October 2, 2015
Goto Year:2014 | 2016
§ 101.1009   System operations.

   (a) The licensee may construct and operate any number of fixed stations
   anywhere  within  the  area  authorized  by  the license without prior
   authorization, except as follows:

   (1) A station would be required to be individually licensed if:

   (i) International agreements require coordination;

   (ii) Submission of an Environmental Assessment is required under § 1.1307 of
   this chapter.

   (iii) The station would affect areas identified in § 1.924 of this chapter.

   (2) Any antenna structure that requires notification to the Federal Aviation
   Administration  (FAA)  must be registered with the Commission prior to
   construction under § 17.4 of this chapter.

   (b) Whenever a licensee constructs or makes system changes as described in
   paragraph  (a) of this section, the licensee is required to notify the
   Commission within 30 days of the change under § 1.947 of this chapter and
   include a statement of the technical parameters of the changed station.

   [ 62 FR 23168 , Apr. 29, 1997, as amended at  63 FR 68984 , Dec. 14, 1998;  69 FR 17959 , Apr. 6, 2004]

   return arrow Back to Top


Goto Section: 101.1007 | 101.1011

Goto Year: 2014 | 2016
CiteFind - See documents on FCC website that cite this rule

Want to support this service?
Thanks!

Report errors in this rule. Since these rules are converted to HTML by machine, it's possible errors have been made. Please help us improve these rules by clicking the Report FCC Rule Errors link to report an error.
hallikainen.com
Helping make public information public