§ 22.946   Construction period for Unserved Area authorizations.

   The construction period applicable to new or modified Cellular facilities
   for which an authorization is granted pursuant to the Unserved Area process
   is one year, beginning on the date the authorization is granted. To satisfy
   this requirement, a Cellular system must be providing service to mobile
   stations operated by subscribers and roamers. The licensee must notify the
   FCC (FCC Form 601) after the requirements of this section are met. See
   § 1.946 of this chapter. See also § 22.949.

   [ 79 FR 72151 , Dec. 5, 2014]

   return arrow Back to Top


Goto Section: 22.943 | 22.947

Goto Year: 2014 | 2016
CiteFind - See documents on FCC website that cite this rule

Want to support this service?
Thanks!

Report errors in this rule. Since these rules are converted to HTML by machine, it's possible errors have been made. Please help us improve these rules by clicking the Report FCC Rule Errors link to report an error.
hallikainen.com
Helping make public information public