  § 74.34   Period of construction; certification of completion of construction.
   (a) Each aural and television broadcast auxiliary station authorized
   under subparts E and F of this part must be in operation within 18
   months from the initial date of grant.
   (b) Each remote pickup broadcast auxiliary station authorized under
   subpart D of this part must be in operation within 12 months from the
   initial date of grant.
   (c) Failure to timely begin operation means the authorization
   terminates automatically.
   (d) Requests for extension of time may be granted upon a showing of
   good cause pursuant to § 1.946(e) of this chapter.
   (e) Construction of any authorized facility or frequency must be
   completed by the date specified in the license and the Commission must
   be notified pursuant to § 1.946 of this chapter.
   [ 68 FR 12763 , Mar. 17, 2003]
   return arrow Back to Top
Subparts A-C [Reserved]
   return arrow Back to Top
Subpart D—Remote Pickup Broadcast Stations
   return arrow Back to Top
Goto Section: 74.32 | 74.401
Goto Year: 2015 |
    2017
CiteFind - See documents on FCC website that
    cite this rule
Want to support this service?
     Thanks!
Report errors in
    this rule. Since these rules are converted to HTML by machine, it's possible errors have been made. Please
    help us improve these rules by clicking the Report FCC Rule Errors link to report an error.
    
    hallikainen.com
    Helping make public information public