Goto Section: 10.340 | 10.400 | Table of Contents

FCC 10.350
Revised as of December 4, 2012
Goto Year:2011 | 2013
§  10.350   CMAS Testing requirements.

   This section specifies the testing that will be required, no later than
   the date of deployment of the CMAS, of CMAS components.

   (a) Required monthly tests. Testing of the CMAS from the Federal Alert
   Gateway to each Participating CMS Provider's infrastructure shall be
   conducted monthly.

   (1) A Participating CMS Provider's Gateway shall support the ability to
   receive a required monthly test (RMT) message initiated by the Federal
   Alert Gateway Administrator.

   (2) Participating CMS Providers shall schedule the distribution of the
   RMT to their CMAS coverage area over a 24 hour period commencing upon
   receipt of the RMT at the CMS Provider Gateway. Participating CMS
   Providers shall determine the method to distribute the RMTs, and may
   schedule over the 24 hour period the delivery of RMTs over geographic
   subsets of their coverage area to manage traffic loads and to
   accommodate maintenance windows.

   (3) A Participating CMS Provider may forego an RMT if the RMT is
   pre-empted by actual alert traffic or if an unforeseen condition in the
   CMS Provider infrastructure precludes distribution of the RMT. A
   Participating CMS Provider Gateway shall indicate such an unforeseen
   condition by a response code to the Federal Alert Gateway.

   (4) The RMT shall be initiated only by the Federal Alert Gateway
   Administrator using a defined test message. Real event codes or alert
   messages shall not be used for the CMAS RMT message.

   (5) A Participating CMS Provider shall distribute an RMT within its
   CMAS coverage area within 24 hours of receipt by the CMS Provider
   Gateway unless pre-empted by actual alert traffic or unable due to an
   unforeseen condition.

   (6) A Participating CMS Provider may provide mobile devices with the
   capability of receiving RMT messages.

   (7) A Participating CMS Provider must retain an automated log of RMT
   messages received by the CMS Provider Gateway from the Federal Alert
   Gateway.

   (b) Periodic C interface testing. In addition to the required monthly
   tests, a Participating CMS Provider must participate in periodic
   testing of the interface between the Federal Alert Gateway and its CMS
   Provider Gateway. This periodic interface testing is not intended to
   test the CMS Provider's infrastructure nor the mobile devices but
   rather is required to ensure the availability/viability of both gateway
   functions. Each CMS Provider Gateway shall send an acknowledgement to
   the Federal Alert Gateway upon receipt of such an interface test
   message. Real event codes or alert messages shall not be used for this
   periodic interface testing.

   [ 73 FR 47558 , Aug. 14, 2008]

   return arrow Back to Top

Subpart D—Alert Message Requirements

   return arrow Back to Top


Goto Section: 10.340 | 10.400

Goto Year: 2011 | 2013
CiteFind - See documents on FCC website that cite this rule

Want to support this service?
Thanks!

Report errors in this rule. Since these rules are converted to HTML by machine, it's possible errors have been made. Please help us improve these rules by clicking the Report FCC Rule Errors link to report an error.
hallikainen.com
Helping make public information public