Goto Section: 32.2422 | 32.2424 | Table of Contents

FCC 32.2423
Revised as of October 1, 2013
Goto Year:2012 | 2014
§  32.2423   Buried cable.

   (a) This account shall include the original cost of buried cable as
   well as the cost of other material used in the construction of such
   plant. This account shall also include the cost of trenching for and
   burying cable run in conduit not classifiable to Account 2441, Conduit
   Systems. Subsidiary record categories, as defined below, are to be
   maintained for nonmetallic buried cable and metallic buried cable.

   (1) Nonmetallic cable. This subsidiary record category shall include
   the original cost of optical fiber cable and other associated material
   used in constructing a physical path for the transmission of
   telecommunications signals.

   (2) Metallic cable. This subsidiary record category shall include the
   original cost of single or paired conductor cable, wire and other
   associated material used in constructing a physical path for the
   transmission of telecommunications signals.

   (b) The cost of pumping water out of manholes and of cleaning manholes
   and ducts in connection with construction work and the cost of permits
   and privileges for the construction of cable and wire facilities shall
   be included in the account chargeable with such construction.

   return arrow Back to Top


Goto Section: 32.2422 | 32.2424

Goto Year: 2012 | 2014
CiteFind - See documents on FCC website that cite this rule

Want to support this service?
Thanks!

Report errors in this rule. Since these rules are converted to HTML by machine, it's possible errors have been made. Please help us improve these rules by clicking the Report FCC Rule Errors link to report an error.
hallikainen.com
Helping make public information public